Construction Updates

Watch construction progress here:

Clarendon 268 Powder house Blvd – View 1 (Somerville, MA)

OxBlue Construction Cameras

 

January 2025

Construction Updates:

Work:
July

Wednesday, July 3rd

RM Pacella will be paving Powder House Blvd to the North Street intersection (weather permitting) and the road will be entirely shut down; there will be no resident access to the parking lot after 8am. Any cars that need to be accessible will need to be relocated out of the parking lot on Wednesday, July 3rd before 8am.

 

June/July

Monday, June 10th

RM Pacella will be milling Alewife Brook Parkway and the Powder House Blvd/North Street Intersection. (Residents should be able to access the driveway)

Later that week, the resident driveway will be reconstructed. Access will be maintained but there will be construction.

 Monday, June 17th – RESCHEDULED to Friday, June 28th & July 3rd

RM Pacella will be paving Alewife Brook Parkway beginning at 8:30am on Friday, June 28th. Paving will continue Wednesday, July 3rd for Powder House Blvd to the North Street intersection (weather permitting) and the road will be entirely shut down; there will be no resident access to the parking lot during the day. Any cars that need to be accessible will need to be relocated out of the parking lot before Wednesday, July 3rd at 8am.

Detour plan for the 1st:

 

April/May

April 22nd – May 3rd Parking Lot Excavation

Beginning Monday April 22nd, the contractor will trench the 34 North Street tenant parking lot, planning to complete work by Friday May 3rd.

During that week, there will be no access to this area between 7am-3pm Monday thru Friday. All open trenchwork will be overlayed with road plates at the end of each working day 3pm which will provide use of available parking spaces in this lot between the hours of 4pm – 7am daily. We encourage tenants to utilize the main lot off of Powderhouse as much as possible.

Building 34 access: 34A, 34B, 34C will be accessible to residents off of the tenant walkway adjacent to community dumpsters, park benches, tenant “garden”.

24 North Street access: 24C, 24B, 24A can be accessed during this time period off of North street at the walkway in between the 24 Building and North Street Veteran’s Playground.  We are coordinating with SHA law enforcement and will have individuals on foot to supervise and re-direct foot traffic if there is any confusion.

  • January 2024

    Phase 1 construction progress on foundation & podium (more…)

  • December 2023 construction updates

    (more…)

  • Week of August 21

    (more…)

  • Week of June 26th

    (more…)

  • Week of June 19th

    (more…)

  • Week of June 5th

    (more…)

  • May week of 15th

    (more…)

  • Week of May 8th- Demolition Complete

    (more…)

  • Week of May 1st- 125 ALEWIFE BROOK PKWY

    (more…)

  • April 13th- Pedestrian Detour

    (more…)