Dellbrook is working their way up retaining wall shared with Stop & Shop – excavating, repair and replacement
Soil is being trucked offsite
Continued work on foundations; rebar coming in this week
Parking spaces by driveway entrance will be available again starting Friday. They will then be re-paved sometime in the next few weeks.
Look ahead:
City will be addressing driveway entrance to improve condition over the next several weeks. More info to be shared.
Underground mechanical will likely start week of September 5th (electrical in main electric room)