Next 3 weeks:
- Soil compaction test set up for Friday for foundation
- Remaining soil stored onsite to be hauled away Monday
- Grade new road, install Roadway binder Monday 19th
- Prep site for foundation work: mobilization of mobile crane, small excavator, commercial auger for pre-drilling and pile driver
- Laydown area for steel in center of site; notched and then will be hoisted and each pile driven into location below the foundation
- Last pile of deliveries for a while was today 6/14
- Demo stairs at corner of 139 ABP; mason sealing up